Week 16: Open for Tours
Time to celebrate! The 2011 Coastal Living Ultimate Beach House is open for tours. Get a sneak peek of the finished product, and find out how you can visit.
moreWeek 15: Moving Day
It’s moving day! Soon the house will be filled with the perfect handpicked art and furniture. We're anxious to see it fully finished, and we know you are too!
moreWeek 14: Refreshing Colors
From aqua blues to relaxing browns, wallpaper and interiors paint are really livening up our 2011 Ultimate Beach House.
moreWeek 13: Counting Down
We're a week or so away from completing the house. Take a look at interior and exterior photos before we hand it over the interior decorators!
moreWeek 12: Wrapping Up Ceilings and Floors
We're putting the finishing touches on construction. Check out the completed ceilings and floors, plus see a preview of the outdoor fireplace.
moreWeek 11: Looking Forward to the Open House
Save the date! The 2011 Ultimate Beach House opens July 29th, so check out these pictures of our almost-finished product.
moreWeek 10: Lights, Cabinets, Tile, and more
We're starting to pull everything together. Take a look inside our Ultimate Beach House and see a preview of the kitchen, landscaping, and light fixtures.
moreWeek 9: Bathroom Tile and Door Installation
Check out an updated photo of the home's exterior, plus images of the bathroom tiles and custom Bolection doors. We're installing both this week!
moreWeek 8: Installing Ceramic Floors and Interior Doors
This week the East Beach team is completing the AZEK deck, laying down flooring, and hanging doors throughout the house. Stay tuned for a preview of the interior decor.
moreWeek 7: Finishing Siding, Shingles, and Trim
Our crew continues exterior shingle and siding work this week, and we're sharing a first look at the great room with its bead board ceilings and wainscoting.
moreWeek 6: Adding the Trim
The exterior trim on the north side is nearly complete! And thankfully, the Ultimate Beach House weathered the storms that swept across the southeast, despite 30 mile-per-hour winds and driving rain.
moreWeek 5: Progress Update
The roof in halfway finished and the interior drywall is 75 percent complete. The 2011 Ultimate Beach House is starting to look more like a home.
moreWeek 4: Landscape Preview
Construction continues to progress smoothly. Landscape plans were approved in mid-April, including a private courtyard and two-level deck overlooking the Chesapeake.
moreWeek 3: Highlighting Special Features
The interior of our 2011 Ultimate Beach house started taking shape in early April. Here' some of our favorite features.
moreWeek 2: Window Installation
The windows were installed in late March letting gorgeous water views shine through.
moreWeek 1: Breaking Ground
Construction on the 2011 house began soon after the holidays—despite the two feet of snow drifts that piled high on our building site!
more